Major shutdown on the Hunter Valley rail network this week

Impressive_new_120_stone_Loram_grinder_1.jpg

There's another major shutdown on the Hunter Valley rail network this week. 

The three-day shutdown is across the coal lines between Kooragang and Maitland as well as the main lines from Muswellbrook to Ulan, Narrabri and Maitland and being conducted by the Australian Rail Track Corporation (ARTC).

The shutdown starts Tuesday 11th from 6:30am, to Friday 14th February 6:30am with 1200 workers conducting over 120 maintenance jobs including removing and replacing 14 kilometres of rail, upgrading approximately 1.5 kilometres of track subgrade across six sites, continue ongoing signal upgrade work between Islington and Sandgate and routine maintenance and defect removal and various other major upgrades. 

ARTC will also welcome the new 120 stone Loram grinder to the Hunter Valley which will improve rail grinding performance.

ARTC Group Executive Hunter Valley Wayne Johnson assured residents and the community ARTC is focused on delivering a safe maintenance shutdown.

“As days of extreme heat can have an impact on the track, such as causing signal faults, circuit breaks or track buckling due to intense heat conditions, we need to carry out this work to ensure the track remains safe, particularly in recent extreme weather conditions,” he said.

“We continue to also carry out spot maintenance as required, to ensure the safety and reliability of the track and limit ‘hot works’ on these days, such as welding or rail grinding to reduce  risk.”

Wayne Johnson said the work requires a total shutdown for work to be carried out as safely as possible.

“Similar to other recent maintenance programs, a scheduled shutdown is required to allow us to access the track for maintenance and upgrades that cannot be done safely when trains are running,” he said.

“We thank our customers, commuters and motorists across the network for their patience while we carry out this important planned maintenance program."

“We remind residents to remain vigilant as there may be more vehicle movements in and out of work sites in residential areas around the work sites.”

Alternative bus services will be provided for impacted customers, and details and schedules can be found at the Transport for NSW website.

The next major maintenance shutdown is scheduled from 1 to 3 April.